NEW QUESTION 161
What is a supplier of a PRINCE2 project responsible for?
- A. Providing resources to deliver the project outputs
- B. Providing the project mandate
- C. Realizing the benefits from the project
- D. Establishing the project's governance
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wikidot.com/senior-supplier
NEW QUESTION 162
Which is a purpose of the Controlling a Stage process?
- A. Enable the Project Board to be provided with sufficient information to authorize the next stage
- B. Enable the organization to understand the work that needs to be done to deliver the project's products
- C. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
- D. Provide a fixed reference point at which acceptance for the project product is confirmed
Answer: C
NEW QUESTION 163
Which of the following statements about stakeholders are true?
1.Someone who thinks they will be affected by a project is a stakeholder on that project
2.Stakeholders may be internal or external to the corporate organization
- A. Only 1 is true
- B. Both 1 and 2 are true
- C. Neither 1 or 2 are true
- D. Only 2 is true
Answer: B
NEW QUESTION 164
What is an off-specification?
- A. A major risk
- B. A type of issue
- C. A quality tolerance
- D. A new requirement
Answer: B
Explanation:
Section: Volume A
NEW QUESTION 165
Who should act as the communication channel between a project and corporate or programme
management?
- A. Project Board
- B. Project Assurance
- C. Project Manager
- D. Project Support
Answer: A
NEW QUESTION 166
How many tasks does the product-based planning technique describe?
- A. Two
- B. One
- C. Three
- D. Four
Answer: D
NEW QUESTION 167
Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.
- A. an off-specification
- B. a threat
- C. a deviation from tolerance
- D. a constraint
Answer: A
NEW QUESTION 168
Which process has the objective of confirming that acceptance criteria have been met?
- A. Controlling a stage
- B. Managing product delivery
- C. Closing a project
- D. Directing a project
Answer: C
NEW QUESTION 169
Which is an objective of the Closing a Project process?
- A. Prepare the plan for the next stage
- B. Produce a Benefits Review Plan to identify what benefits are expected
- C. Assess any benefits that have already been realized
- D. Check that all benefits are realized before closing a project
Answer: C
Explanation:
Section: Volume A
NEW QUESTION 170
Which is a true statement about PRINCE2 event-driven controls?
- A. Event-driven controls are produced at the frequency defined in a Work Package
- B. Event-driven controls are used for decision making
- C. Checkpoint Reports are event-driven controls
- D. Event-driven controls take place at predefined periodic intervals
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 171
Where should a team manager look for information about the quality required for a product?
- A. Team plan
- B. Product description
- C. Project initiation documentation
- D. Quality management approach
Answer: B
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2
NEW QUESTION 172
Which is a benefit of using PRINCE2?
- A. Includes many of the proven planning techniques, such as critical path analysis
- B. Can be used tomanage both projects and programmes
- C. Provides for the efficient and economic use of management time
- D. Is a method specifically designed for technical projects
Answer: C
NEW QUESTION 173
Which is a typical core activity within configuration management?
- A. Communication
- B. Assessment
- C. Quality control
- D. Status accounting
Answer: D
NEW QUESTION 174
Which of the following statements about quality assurance and Project Assurance is true?
- A. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
- B. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
- C. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
- D. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
Answer: A
NEW QUESTION 175
Which describes an off-specification?
- A. The addition of an improvement to a product description
- B. A prototype demonstrating a possible design solution
- C. The production of more than the defined quantity of a specialist product
- D. An interdependency between products that was previously unidentified
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-change-control/
NEW QUESTION 176
What do customer's quality expectations identify?
- A. Skills required to develop the project product
- B. Standards that must be used in order to meet the level of quality needed
- C. Reviewer names for each product
- D. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
Answer: B
NEW QUESTION 177
Which role is responsible for the quality of the specialist products delivered in the project?
- A. Project assurance
- B. Senior user
- C. Senior supplier
- D. Executive
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx
NEW QUESTION 178
Why is a Project Brief produced?
- A. To provide a full and firm foundation for the initiation of a project
- B. To be used by the Project Board as a basis for reviewing the progress of a project
- C. To record the strategies andmanagement controls to be used by a project
- D. To act as a trigger for the Starting up a Project process
Answer: A
NEW QUESTION 179
......
How to study the PR2F Exam
There are two main types of resources for preparation of certification exams first there are the study guides and the books that are detailed and suitable for building knowledge from ground up then there are video tutorial and lectures that can somehow ease the pain of through study and are comparatively less boring for some candidates yet these demand time and concentration from the learner. Smart Candidates who want to build a solid foundation in all exam topics and related technologies usually combine video lectures with study guides to reap the benefits of both but there is one crucial preparation tool as often overlooked by most candidates the practice exams. Practice exams are built to make students comfortable with the real exam environment. Statistics have shown that most students fail not due to that preparation but due to exam anxiety the fear of the unknown. PracticeTorrent expert team recommends you to prepare some notes on these topics along with it don't forget to practice Exin PR2F exam dumps which been written by our expert team, Both these will help you a lot to clear this exam with good marks.
Exam Valid Dumps with Instant Download Free Updates: https://actual4test.practicetorrent.com/PRINCE2Foundation-practice-exam-torrent.html